The Standard Residences Hua Hin
Expected completion Date: 30 Sep 2026
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Pile-driving work is completed 100%
Tower A: Structual work is finished up to 8 th floor
Tower B: Structual work is finished up to 2nd floor
Tower C: Structual work is finished up to 4th floor
Tower D: Structual work is finished up to 4th floor
Tower E: Structual work is finished up to 4th floor
Tower F: Structual work is finished up to 4th floor
Tower G: Structual work is finished up to 4th floor
Tower H: Structual work is finished up to 4th floor
Tower I: Structual work is finished up to 4th floor -
Systems installation
Tower A: Eletrical systems are finished up to 7 th fl., pumbling systems on 7 th fl.
Tower B: Eletrical systems are finished up to 1st fl. pumbling systems on 1 st fl
Tower C: Eletrical systems are finished up to 4th fl. pumbling systems on 4th fl. A/C systems on 4th fl
Tower D: Eletrical systems are finished up to 4th fl., pumbling systems on 4th fl. A/C systems on 4th fl.
Tower E: Eletrical systems are finished up to 4th fl. pumbling systems on 4th fl. A/C systems on 4th fl.
Tower F: Eletrical systems are finished up to 4th fl, pumbling systems on 4th fl. A/C systems on 4th fl.
Tower G: Eletrical systems are finished up to 4th fl. pumbling systems on 4th fl. A/C systems on 4th fl.
Tower H: Eletrical systems are finished up to 4th floor, pumbling systems on 4th fl. A/C systems on 4th fl.
Tower I: Eletrical systems are finished up to 4th floor, pumbling systems on 4th fl. A/C systems on 4th fl. -
Architectural Work
Tower A: Wall construction is finished up to 6 th floor
Tower B: Wall construction is finished up to 2nd floor
Tower C: Wall construction is finished up to 4th floor
Tower D: Wall construction is finished up to 4th floor
Tower E: Wall construction is finished up to 4th floor
Tower F: Wall construction is finished up to 4th floor
Tower G: Wall construction is finished up to 4th floor
Tower H: Wall construction is finished up to 4th floor
Tower I: Wall construction is finished up to 4th floor
In progress of QC End Product