The Standard Residences Hua Hin

Expected completion Date: 30 Sep 2026
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Pile-driving work is completed 100%
    Tower A: Structual work is finished up to 8 th floor
    Tower B: Structual work is finished up to 2nd floor
    Tower C: Structual work is finished up to 4th floor
    Tower D: Structual work is finished up to 4th floor
    Tower E: Structual work is finished up to 4th floor
    Tower F: Structual work is finished up to 4th floor
    Tower G: Structual work is finished up to 4th floor
    Tower H: Structual work is finished up to 4th floor
    Tower I: Structual work is finished up to 4th floor
  • Systems installation
    Tower A: Eletrical systems are finished up to 7 th fl., pumbling systems on 7 th fl.
    Tower B: Eletrical systems are finished up to 1st fl. pumbling systems on 1 st fl
    Tower C: Eletrical systems are finished up to 4th fl. pumbling systems on 4th fl. A/C systems on 4th fl
    Tower D: Eletrical systems are finished up to 4th fl., pumbling systems on 4th fl. A/C systems on 4th fl.
    Tower E: Eletrical systems are finished up to 4th fl. pumbling systems on 4th fl. A/C systems on 4th fl.
    Tower F: Eletrical systems are finished up to 4th fl, pumbling systems on 4th fl. A/C systems on 4th fl.
    Tower G: Eletrical systems are finished up to 4th fl. pumbling systems on 4th fl. A/C systems on 4th fl.
    Tower H: Eletrical systems are finished up to 4th floor, pumbling systems on 4th fl. A/C systems on 4th fl.
    Tower I: Eletrical systems are finished up to 4th floor, pumbling systems on 4th fl. A/C systems on 4th fl.
  • Architectural Work
    Tower A: Wall construction is finished up to 6 th floor
    Tower B: Wall construction is finished up to 2nd floor
    Tower C: Wall construction is finished up to 4th floor
    Tower D: Wall construction is finished up to 4th floor
    Tower E: Wall construction is finished up to 4th floor
    Tower F: Wall construction is finished up to 4th floor
    Tower G: Wall construction is finished up to 4th floor
    Tower H: Wall construction is finished up to 4th floor
    Tower I: Wall construction is finished up to 4th floor
    In progress of QC End Product