PROJECT PROGRESS
The Standard Residences Hua Hin
Expected completion Date: September 2026
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Pile-driving work is completed 100%
-
Systems installation
Tower A: Eletrical systems are finished up to 8 th fl., pumbling systems on 8 th fl. A/C systems on 3 rd
Tower B: Eletrical systems are finished up to 1st fl. pumbling systems on 1 st fl
Tower C:Eletrical systems are finished up to 4th fl. pumbling systems on 4th fl. A/C systems on 4th fl
Tower D: Eletrical systems are finished up to 4th fl. , pumbling systems on 4th fl. A/C systems on 4th fl.
Tower E: Eletrical systems are finished up to 4th fl. pumbling systems on 4th fl. A/C systems on 4th fl.
Tower F: Eletrical systems are finished up to 4th fl, pumbling systems on 4th fl. A/C systems on 4th fl.
Tower G: Eletrical systems are finished up to 4th fl. pumbling systems on 4th fl.A/C systems on 4th fl.
Tower :H Eletrical systems are finished up to 4th floor, pumbling systems on 4th fl. A/C systems on 4th fl.
Tower I: Eletrical systems are finished up to 4th floor, pumbling systems on 4th fl. A/C systems on 4th fl. -
Architectural Work
Tower A : Wall construction is finished up to 7 th floor
Tower B : Wall construction is finished up to 2nd floor
Tower C : Wall construction is finished up to 4th floor
Tower D : Wall construction is finished up to 4th floor
Tower E : Wall construction is finished up to 4th floor
Tower F : Wall construction is finished up to 4th floor
Tower G : Wall construction is finished up to 4th floor
Tower H : Wall construction is finished up to 4th floor
Tower I : Wall construction is finished up to 4th floor
In progress of QC End Product