THE BASE Ratchada 19
Expected completion Date: 31 Aug 2026
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Pile-driving work is completed 100%
Strutural work is finished up to 7th floor -
Systems installation
Installations of eletrical systems are finished up to 7 th floor, pumbling systems on 7 th floor and A/C systems are finished up to 6 th floor
-
Architectural Work
Wall construction is finished up to 7th floor