dcondo cove Phuket

Expected completion Date: June 2027
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Pile-driving work is completed 100%
    Tower A:Structual work is finished up to 2 nd floor
    Tower B: Structual work is finished up to 2 nd floor
    Tower C: Structual work is finished up to 6 th floor
    Tower D: Structual work is finished up to 2 nd floor
  • Systems installation
    Tower A: Eletric work is finished up to 1 st floor
    Tower A: Pumbling work is finished up to
    Tower A: A/C work is finished up to
    Tower B: Eletric work is finished up to 1 st floor
    Tower B: Pumbling work is finished up to
    Tower B: A /C work is finished up to
    Tower C: Eletric work is finished up to 3 rd floor
    Tower C: Pumbling work is finished up to 3 rd floor
    Tower C: A / C work is finished up to
    Tower D: eletric work is finished up to 1 st floor
    Tower D: Pumbling work is finished up to 1 st floor
  • Architectural Work
    Tower C: Wall construction is finished is 1 st floor