dcondo cove Phuket
Expected completion Date: June 2027
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Pile-driving work is completed 100%
Tower A:Structual work is finished up to 2 nd floor
Tower B: Structual work is finished up to 2 nd floor
Tower C: Structual work is finished up to 6 th floor
Tower D: Structual work is finished up to 2 nd floor -
Systems installation
Tower A: Eletric work is finished up to 1 st floor
Tower A: Pumbling work is finished up to
Tower A: A/C work is finished up to
Tower B: Eletric work is finished up to 1 st floor
Tower B: Pumbling work is finished up to
Tower B: A /C work is finished up to
Tower C: Eletric work is finished up to 3 rd floor
Tower C: Pumbling work is finished up to 3 rd floor
Tower C: A / C work is finished up to
Tower D: eletric work is finished up to 1 st floor
Tower D: Pumbling work is finished up to 1 st floor -
Architectural Work
Tower C: Wall construction is finished is 1 st floor