PROJECT PROGRESS
VIA Ari
Expected completion Date: 31 August 2026
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Pile-driving work is completed 100%
Structure work is finished up to 27th floor -
Systems installation
Installation of eletrical systems is finished up to 26 th floor
Installation of pumpling systems is finished up to 26 th floor
Installation of A/C systems is finished up to 26 th floor -
Architectural Work
Wall Constuction is finished up to 27 th floor
In progress of QC End Product