Date: June 2026
Date: June 2026
Date: June 2026
Date: May 2026
Date: May 2026
Date: May 2026
Date: May 2026
Date: April 2026
Date: April 2026
Date: April 2026
Date: April 2026
Date: March 2026
Date: March 2026
Date: March 2026
Date: March 2026
Date: February 2026

VIA Ari

Expected completion Date: 31 August 2026
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Pile-driving work is completed 100%
    Structure work is finished up to 27th floor
  • Systems installation
    Installation of eletrical systems is finished up to 26 th floor
    Installation of pumpling systems is finished up to 26 th floor
    Installation of A/C systems is finished up to 26 th floor
  • Architectural Work
    Wall Constuction is finished up to 27 th floor
    In progress of QC End Product