PROJECT PROGRESS
PTY Residence Sai 1
Expected completion Date: 31 May 2027
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Pile-driving work is completed 100%
Structual work is finished up to 24th floor -
Systems installation
Installations of eletrical systems are finished up to 11 st floor, pumbling systems on 11 st floor and A/C systems on 9th floor
-
Architectural Work
Wall construction is finished up to 15th floor