Date: September 2023
Date: September 2023
Date: September 2023
Date: September 2023

dcondo Sand Hatyai

Expected completion Date : September 2024
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Pile driving work all completed for Tower A-B.
    Foundation of tower A is 80.90%.
    Treatment Tank work is 29% for Tower B.
  • Systems installation
    Installation of pumbling systems underway on Floor 1
    Sanitary system work is 1 st floor on Tower B.
  • Architectural Work