PROJECT PROGRESS

dcondo Sand Hatyai
Expected completion Date : September 2024
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Pile driving work all completed for Tower A-B.
Foundation of tower A is 80.90%.
Treatment Tank work is 29% for Tower B. -
Systems installation
Installation of pumbling systems underway on Floor 1
Sanitary system work is 1 st floor on Tower B. -
Architectural Work