dcondo Sand Hatyai
Expected completion Date : September 2024
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Pile-driving work all completed.
Floor structual work is completed for Tower A
Floor structual work is completed for Tower B -
Systems installation
TOWER A Installation of eletric work is completed on Floor 4,
Installation of pumbling systems underway on Floor3 , Installation of A/C systems underway on Floor 3
TOWER B Installation of eletric work is completed on Floor 4,
Installation of pumbling systems underway on Floor3 , Installation of A/C systems underway on Floor 3 -
Architectural Work
Tower A : Wall construction is completed on Floor 5
Tower B : Wall construction is completed on Floor 6