dcondo Sand Hatyai

Expected completion Date : September 2024
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Pile-driving work all completed.
    Floor structual work is completed on floor 7 for Tower A.
    Floor structual work is completed for Tower B.
  • Systems installation
    TOWER A: Installation of eletric work is completed on Floor 3, Installation of pumbling systems underway on Floor4, Installation of A/C systems underway on Floor 2.
    TOWER B: Installation of eletric work is completed on Floor 4, Installation of pumbling systems underway on Floor5 , Installation of A/C systems underway on Floor 2.
  • Architectural Work
    Tower A: Wall construction is completed on Floor 5.
    Tower B: Wall construction is completed on Floor 6.