Dcondo Vale Sriracha

Expected completion Date : September 2024
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Pile-driving work all completed.
    Structual work is completed for Tower A
    Structual work is completed for Tower B
  • Systems installation
    TOWER A Installation of eletric work is completed on Floor6,
    Installation of pumbling systems underway on Floor6 ,
    Installation of A/C systems underway on Floor 4
    TOWER B Installation of eletric work is completed on Floor6,
    Installation of pumbling systems underway on Floor6 ,
    Installation of A/C systems underway on Floor 4
  • Architectural Work
    Tower A :Wall construction is completed on Floor 7
    Tower B :Wall construction is completed on Floor 7