Date: January 2018
Date: January 2018
Date: January 2018
Date: January 2018
Date: December 2017
Date: December 2017
Date: December 2017
Date: December 2017
Date: December 2017
Date: December 2017
Date: December 2017
Date: December 2017
Date: September 2017
Date: September 2017
Date: September 2017
Date: September 2017


Expected completion Date : March 2019
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.

  • Structural Work
    Structural flooring work underway on Floor 30
  • Systems installation
    Installation of A/C systems underway on Floor 1-26
  • Architectural Work
    Plastering work underway on Floor 1-20