THE LINE Phahon - Pradipat
Expected completion Date : November 2019
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Flooring work has completed up to Floor 5
-
Systems installation
System installation work underway on Floor 5 parking facility
-
Architectural Work