kawa HAUS Sukhumvit 77
Expected completion Date : January 2019
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Structural work completed on Floor 7.
-
Systems installation
Installation of in-wall conduits underway.
-
Architectural Work
Bricklaying work underway.