kawa HAUS Sukhumvit 77

Expected completion Date : January 2020
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Structural work completed on Deck Level of Tower B1.
  • Systems installation
    Installation of electrical systems underway on Floor 7.
    Installation of pumbling systems underway on Floor 5.
    Installation of A/C systems underway on Floor 4 of Tower B1.
  • Architectural Work
    Bricklaying work underway on Floor 6 of Tower B1.