dcondo Hatyai

Expected completion Date : July 2019
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Structural flooring work completed on Deck Level of both Tower A and Tower B
  • Systems installation
    Installation of electrical systems underway on Floor 7. Installation of pumbling systems underway on Floor 7. Installation of A/C systems underway on Floor 2 of Tower A
  • Architectural Work
    Architectural work is completed on Floor 7 of Tower A