dcondo Hatyai

Expected completion Date : September 2024
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Pile-driving work all completed.
    Floor structual work is completed for Tower A.
    Floor structual work is completed for Tower B.
  • Systems installation
    TOWER A Installation of eletric work is completed on Floor 4.
    , Installation of pumbling systems underway on Floor 3.
    , Installation of A/C systems underway on Floor 3.
    TOWER B Installation of eletric work is completed on Floor 4.
    , Installation of pumbling systems underway on Floor 3.
    , Installation of A/C systems underway on Floor 3.
  • Architectural Work
    Tower A : Wall construction is completed on Floor 5.
    Tower B : Wall construction is completed on Floor 6.