XT Ekkamai
Expected completion Date : October 2020
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Structural work is completed on Floor 38.
-
Systems installation
Installation of electrical systems underway on Floor 38.
Installation of pumbling systems underway on Floor 38.
Installation of A/C systems underway on Floor 38. -
Architectural Work
Architectural is completed on Floor 38 and QC Control is underway.