XT Ekkamai

Expected completion Date : December 2020
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Structural work is completed on Floor 36.
  • Systems installation
    Installation of electrical systems underway on Floor 19.
    Installation of pumbling systems underway on Floor 19.
    Installation of A/C systems underway on Floor 19.
  • Architectural Work
    Wall construction is completed on Floor 25.