THE BASE Central-Phuket

Expected completion Date : May 2020
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Structural work completed on Floor 8 for Tower A.
  • Systems installation
    Installation of electrical systems underway on Floor 8.
    Installation of pumbling systems underway on Floor 8.
    Installation of A/C systems underway on Floor 8 of Tower A.
  • Architectural Work
    Architectural is completed on Floor 8 and QC Control is underway on Floor 7 of Tower A.