PROJECT PROGRESS
dcondo kiri
Expected completion Date: 31 July 2026
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Pile-driving work is completed 100%
Tower A: Structual work is finished up to 8th floor
Tower B: Structual work is finished up to 8th floor -
Systems installation
Tower A: Installations of eletrical systems are finished up to 8th floor, pumbling systems on 8th floor and A/C systems on 8th floor
Tower B: Installations of eletrical systems are finished up to 8th floor, pumbling systems on 8th floor and A/C systems on 8th floor -
Architectural Work
Tower A: Wall construction is finished up to 8th floor
Tower B: Wall construction is finished up to 8th floor
In progress of QC End Product