THE BASE Srichan Khonkaen

Expected completion Date: 30 July 2026
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Pile-driving work is completed 100%
    Tower A: Structual work is finished up to 8th floor
    Tower B: Structual work is finished up to 8th floor
  • Systems installation
    Tower A: Installations of eletrical systems are finished up to 8th floor, pumbling systems on 8th floor and A/C systems on 8th floor
    Tower B: Installations of eletrical systems are finished up to 8th floor, pumbling systems on 8th floor and A/C systems on 8th floor
  • Architectural Work
    Tower A: Wall construction is finished up to 8th floor
    Tower B: Wall construction is finished up to 8th floor
    In progress of QC End Product